Schools and Domestic

SCHOOLS AND DOMESTIC

KMS were appointed by South & City College Birmingham as principal contractor to manage, install and complete the contract throughout the six-week main summer term holiday.

Phase 1: The initial works were to strip out the complete area of painting and decorating teaching bays, ceilings, staircases, air conditioning and electrics.

Phase 2: KMS constructed sixteen teaching bays using Gyproc stud and plasterboard's which formed mock living-rooms & bedrooms etc and included all plastering, doors, frames, architraves, and skirting as well as fireplaces and staircases to enable the students to learn their trade.
A new Painting & Decorating area was constructed on top of the existing mezzanine floor.

Electrics: The electrical works involved completely new three phase sub-mains with hard wired 110V transformers feeding multiple commando points with emergency lock off stop facility and new microwave LED strip lights and safety emergency escape lighting.

Phase 3: Once the site was completed and cleared, we then painted the ground floor concrete hardstanding using a resin-based floor paint in readiness for that area to be used as a training area for the mechanic apprentices.

This was a fast-track project carried out, completed on time and within budget. Yet another satisfied customer of Koncept Maintenance Support Ltd.


A local School contacted us & asked if we could convert a store room in to a first aid and rest room. They are delighted with the result. Completed this week ready for when the School re-opens.


Aston University, Birmingham. Phase three completed at Aston University, Birmingham. All of the new full height double glazed class rooms are installed and will be ready for use for when the students return. As part of this project we have also installed new air ducting to the rooms to provide a fresh air supply, electrical and data installations, roofing works and also flooring and decorating throughout.


Aston University, Birmingham. The KMS team were asked to design & install a multi faith wash & hygiene room. This involved isolating and removing existing plumbing, installing new shower heads, a water trough,  and complete electrical works also.


Moisture resistant sealed led lights were used, carpentry works, wall panelling, safety Altro flooring and decorating were all completed throughout.


Aston University, Birmingham. This project involved supplying & installing 10 mm toughened, double glazed partition walls to provide extra learning spaces, converting store cupboards in to workable offices. This included installing new suspended ceilings, full electrical & data installation, air conditioning, decorating and sliding glass windows cut in to the existing wall.



Ormiston Academy. To supply and install acoustic walls to form computer teaching rooms. Consisting of 70mm Gyproc stud, sound insulation boards, tape & jointing, decorating and new fire doors & frames throughout.


A project to cut out existing walls and build a new reception for Ryders Green School with white gloss finished veneer doors and office furniture including all decorating and new electrics.